Electrical and Fibre Works Continue

In what seems to be Manchester’s wettest week in May ever, our groundwork and electrical contractors have continued…we’re making a bit of a mess of  the Manchester Technopark at the moment, what with fibre contractors digging up the road, and the groundworks contractors digging up…well everything really!

Today our generator cables have been buried in the trench and the work on the generator compound is almost complete.

Fibrespan came on-site today to start the work to give us one of our diverse routes between Turing House and Reynolds House.

All these works should be completed by the end of the week.

This entry was posted on 20/05/2009 in Turing House Datacentre Build by Daniel Keighron-Foster.