Miscellaneous works continue

This week’s been rather hectic with various works ongoing:

  • Main power panel being connected up to the mains for power-on tomorrow (Friday)
  • First two air conditioners being piped up to the roof where the external condensors will live
  • Generator compound being constructed and trenches dug for the generator cables to go back to the building
  • Cable trays being installed for network and power cables
  • Metering being installed by United Utilities
  • Other miscellaneous work too tedious to mention!
  • Fire suppression and VESDA system being designed.

It’s been rather hectic with various contractors being on-site at the same time, but it’s nice to see the bulk of the work coming together.

Fingers crossed for the power switch-on tomorrow!

This entry was posted on 14/05/2009 in Turing House Datacentre Build by Daniel Keighron-Foster.